Management of projects for corrective and preventive measures with regard to environmental impact. Environmentally sustainable construction works. Joint committees for the environmental and social monitoring of works. Green infrastructure.

Learn about some of the actions we have implemented with regard to the ENVIRONMENTAL WORKS MANAGEMENT
by browsing our files on outstanding cases.

Image

Environmental assistance on concessionary works on the C-17 road, Vic – Ripoll section (Barcelona)
-
CEDINSA


Environmental assistance on concessionary works on the C-17 road, Vic – Ripoll section (Barcelona)

-

CEDINSA

  • Environmental consulting and coordination throughout the duration of the works.
  • Project to widen the C-17 road between KP 75+400 and 93+500.
  • Compliance with Environmental Impact Statement and control of environmental vectors.

Environmental assistance on concessionary works on the C-17 road, Vic – Ripoll section (Barcelona)

CEDINSA

  • Environmental consulting and coordination throughout the duration of the works.
  • Project to widen the C-17 road between KP 75+400 and 93+500.
  • Compliance with Environmental Impact Statement and control of environmental vectors.

Image

Environmental management of works to widen the Eix Transversal trunk road. Section: Cervera – Manresa
-
CEDINSA


Environmental management of works to widen the Eix Transversal trunk road. Section: Cervera – Manresa

-

CEDINSA

  • C-25 road , KP 82+000 to 236+000  from Cervera to Manresa
  • Monitoring of environmental impacts and environmental quality of the vectors of the work and surrounding area.
  • Implementation of corrective measures for environmental impact.

Environmental management of works to widen the Eix Transversal trunk road. Section: Cervera – Manresa

CEDINSA

  • C-25 road , KP 82+000 to 236+000  from Cervera to Manresa
  • Monitoring of environmental impacts and environmental quality of the vectors of the work and surrounding area.
  • Implementation of corrective measures for environmental impact.

Image

Environmental management of work on infrastructure at the Port of Badalona (Barcelona)
-
MARINA BADALONA


Environmental management of work on infrastructure at the Port of Badalona (Barcelona)

-

MARINA BADALONA

  • Occupying approximately 1 km of coast and a total area of  28.65 ha.
  • Water surface: 16.55
  • Dyke 700 m in length
  • Fishing dock: 18,500 m2 on land and 20.500 m2 on water, with capacity for 111 mooring places

Environmental management of work on infrastructure at the Port of Badalona (Barcelona)

MARINA BADALONA

  • Occupying approximately 1 km of coast and a total area of  28.65 ha.
  • Water surface: 16.55
  • Dyke 700 m in length
  • Fishing dock: 18,500 m2 on land and 20.500 m2 on water, with capacity for 111 mooring places

Image

Environmental management of works on Line 9 of the Metro de Barcelona underground system
-
Payma Cotas, SAU


Environmental management of works on Line 9 of the Metro de Barcelona underground system

-

Payma Cotas, SAU

  • 3.9 km section of TMB Line 9, between Zona Universitària and Sagrera – Meridiana stations
  • Attendance of meetings between owners and environmental body (Mixed Commission)
  • Management of 860,000 m3 from tunnelling work.
  • Treatment and management of water from tunnelling work (WWTSs)
  • Control of noise pollution from  access chamber and station shafts.

Environmental management of works on Line 9 of the Metro de Barcelona underground system

Payma Cotas, SAU

  • 3.9 km section of TMB Line 9, between Zona Universitària and Sagrera – Meridiana stations
  • Attendance of meetings between owners and environmental body (Mixed Commission)
  • Management of 860,000 m3 from tunnelling work.
  • Treatment and management of water from tunnelling work (WWTSs)
  • Control of noise pollution from  access chamber and station shafts.

Image

Environmental management of works to convert the Segarra – Garrigues system into an irrigation system.
-
Aigües del Segarra


Environmental management of works to convert the Segarra – Garrigues system into an irrigation system.

-

Aigües del Segarra

  • Environmental monitoring of the works to concentrate plots, primary network, secondary and distribution network of the Segarra – Garrigues.
  • Control of vectors
  • Design of specific environmental monitoring plans for each work, and monthly monitoring reports.
  • Attendance at mixed commission meetings.

Environmental management of works to convert the Segarra – Garrigues system into an irrigation system.

Aigües del Segarra

  • Environmental monitoring of the works to concentrate plots, primary network, secondary and distribution network of the Segarra – Garrigues.
  • Control of vectors
  • Design of specific environmental monitoring plans for each work, and monthly monitoring reports.
  • Attendance at mixed commission meetings.

Image

Environmental monitoring and control of works at the Port of Barcelona
-
AUTORITAT PORTUÀRIA DE BARCELONA


Environmental monitoring and control of works at the Port of Barcelona

-

AUTORITAT PORTUÀRIA DE BARCELONA

  • Environmental monitoring of works carried out at the Port of Barcelona.
  • Air and water quality, waste management
  • Characterisation of dredged material in accordance with CEDEX.

Environmental monitoring and control of works at the Port of Barcelona

AUTORITAT PORTUÀRIA DE BARCELONA

  • Environmental monitoring of works carried out at the Port of Barcelona.
  • Air and water quality, waste management
  • Characterisation of dredged material in accordance with CEDEX.