Human activities consistent with a green and healthy future. Environmental permits. Green cities. Law on Environmental Assessment.

Learn about some of the actions we have implemented with regard to the ENVIRONMENTAL ASSESSMENT OF PLANS, PROGRAMMES AND PROJECTS
by browsing our files on outstanding cases.

Image

Environmental Impact Study of measures to transform the irrigable area of the Segarra-Garrigues canal into irrigated land.
-
INFRAESTRUCTURES.CAT


Environmental Impact Study of measures to transform the irrigable area of the Segarra-Garrigues canal into irrigated land.

-

INFRAESTRUCTURES.CAT

  • Area transformed into irrigated land: 100,000 Ha.
  • Water supply: 342 Hm3/year.
  • Sources: Rialb reservoir, main canal (80 km), Albagés Dam (80 Hm3) and catchment from the River Segre  (69 Hm3/year)
  • Cost of corrective measures: €18.9 million

Environmental Impact Study of measures to transform the irrigable area of the Segarra-Garrigues canal into irrigated land.

INFRAESTRUCTURES.CAT

  • Area transformed into irrigated land: 100,000 Ha.
  • Water supply: 342 Hm3/year.
  • Sources: Rialb reservoir, main canal (80 km), Albagés Dam (80 Hm3) and catchment from the River Segre  (69 Hm3/year)
  • Cost of corrective measures: €18.9 million

Image

Environmental Impact Study Widening of C-25 Eix Transversal trunk road. Section: Les Oluges-Manresa. (Lleida)
-
UTE EUROPRINCIPIA - GPO


Environmental Impact Study Widening of C-25 Eix Transversal trunk road. Section: Les Oluges-Manresa. (Lleida)

-

UTE EUROPRINCIPIA - GPO

  • Widening between PK 87+700 and PK 132+300.
  • Length: 44.6 km
  • Budget for corrective measures: €1.4 million
  • Total budget: €170 million.

Environmental Impact Study Widening of C-25 Eix Transversal trunk road. Section: Les Oluges-Manresa. (Lleida)

UTE EUROPRINCIPIA - GPO

  • Widening between PK 87+700 and PK 132+300.
  • Length: 44.6 km
  • Budget for corrective measures: €1.4 million
  • Total budget: €170 million.

Image

Environmental Impact Study of the new tram system between Bellaterra and Montcada i Reixac (Barcelona)
-
INFRAESTUCTURES.CAT


Environmental Impact Study of the new tram system between Bellaterra and Montcada i Reixac (Barcelona)

-

INFRAESTUCTURES.CAT

  • 12.3 km urban light railway line communicating the towns of Bellaterra (UAB), Cerdanyola , Ripollet and Montcada i Reixac.
  • Budget for corrective measures: €610,000
  • Total investment: €228 million

Environmental Impact Study of the new tram system between Bellaterra and Montcada i Reixac (Barcelona)

INFRAESTUCTURES.CAT

  • 12.3 km urban light railway line communicating the towns of Bellaterra (UAB), Cerdanyola , Ripollet and Montcada i Reixac.
  • Budget for corrective measures: €610,000
  • Total investment: €228 million

Image

Environmental Impact Study FMB project for Line 9. Section 1: Airport-Logistic Park
-
INFRAESTRUCTURES.CAT


Environmental Impact Study FMB project for Line 9. Section 1: Airport-Logistic Park

-

INFRAESTRUCTURES.CAT

  • 9 km underground section between Barcelona Airport T1 and Logistic Park in the city of Barcelona.
  • Possible effects on protected aquifers in the Llobregat Delta
  • Budget for corrective measures: €1.2 million
  • Overall budget: €400 million.

Environmental Impact Study FMB project for Line 9. Section 1: Airport-Logistic Park

INFRAESTRUCTURES.CAT

  • 9 km underground section between Barcelona Airport T1 and Logistic Park in the city of Barcelona.
  • Possible effects on protected aquifers in the Llobregat Delta
  • Budget for corrective measures: €1.2 million
  • Overall budget: €400 million.

Image

Environmental Impact Study Widening of C-25 Eix Transversal trunk road. Section: Les Oluges-Manresa. (Lleida)
-
GISA


Environmental Impact Study Widening of C-25 Eix Transversal trunk road. Section: Les Oluges-Manresa. (Lleida)

-

GISA

  • Widening between PK 87+700 and PK 132+300.
  • Length: 44.6 km
  • Budget for corrective measures: €1.4 million
  • Total budget: €170 million.

Environmental Impact Study Widening of C-25 Eix Transversal trunk road. Section: Les Oluges-Manresa. (Lleida)

GISA

  • Widening between PK 87+700 and PK 132+300.
  • Length: 44.6 km
  • Budget for corrective measures: €1.4 million
  • Total budget: €170 million.

Image

Corrective measures on environmental impact of work on Ferreries link road (Minorca)
-
FERROVIAL AGROMAN S.A


Corrective measures on environmental impact of work on Ferreries link road (Minorca)

-

FERROVIAL AGROMAN S.A

  • 4.2 km trunk and one tunnel
  • 89,000 mhydro seedings
  • Searches for sea turtle
  • Nursery plant production
  • Protection ethnographic heritage
  • 900 macoustic screens
  • Budget: €23 million

Corrective measures on environmental impact of work on Ferreries link road (Minorca)

FERROVIAL AGROMAN S.A

  • 4.2 km trunk and one tunnel
  • 89,000 mhydro seedings
  • Searches for sea turtle
  • Nursery plant production
  • Protection ethnographic heritage
  • 900 macoustic screens
  • Budget: €23 million